update on Twitter

Council votes unanimously to extend the completion date for the Carolina Theatre and InterContinental Hotel in Uptown from Dec. 31, 2023 to Dec. 31, 2025, with an additional $2M in city funding from the Tourism Fund.
Queen City Nerve

The restoration project is currently 70% complete. Asbestos abatement, contaminated groundwater, remediation of lead paint, partnering with a private hotel developer, and façade restoration are listed as reasons for slowed construction at the historic site.

  • Thanks 1
Link to comment
Share on other sites

That is what I can not figure out from these news articles are they still short $13 M or what.   Because this has taken so long they have seen their costs increase greatly of course.  Plus there were hidden issues that had to be taken care of especially when  you are dealing with an old building like this.  @CLT Development do you know anything more about this are they still short money?  

  • Like 1
Link to comment
Share on other sites

13 minutes ago, KJHburg said:

That is what I can not figure out from these news articles are they still short $13 M or what.   Because this has taken so long they have seen their costs increase greatly of course.  Plus there were hidden issues that had to be taken care of especially when  you are dealing with an old building like this.  @CLT Development do you know anything more about this are they still short money?  

I can't believe that we will have to wait more years for this project to be completed.  Holy crap! we sold the facility to the wrong foundation for $1. God knows what kind of great facility we could have had if we hadn't been so stupid and given to the wrong foundation. I hope that the head of the foundation is investigated as he certainly didn't buy the old theater for the purpose of bringing the city forward. I wonder what it took to convince the city council or whomever to approve the delay? In the real world, when a person defaults on a contract, they pay a fine.  The foundation is asking, and obviously getting, a reward and an extension. Over ten years and we still don't even have the renovated theater. Take the place back and sell it to someone that is honest and responsible. 

Edited by Larry Singer
  • Thanks 1
  • Confused 4
Link to comment
Share on other sites

  • 2 months later...

By Thanksgiving....

from the Biz Journal today

""Foundation For The Carolinas CEO Cathy Bessant expects the restored Carolina Theatre to open by Thanksgiving — and promises the performance and community events hub will quickly carve a new niche in Charlotte civic life.

Bessant, during an interview Tuesday with CBJ at the foundation’s uptown headquarters, took over as CEO this month. The foundation’s board named her CEO in September as the full-time replacement for Michael Marsicano, who retired a year ago after 23 years at the helm. ""

Cathy Bessant's new role as foundation CEO begins with long-delayed Carolina Theatre renovation - Charlotte Business Journal (bizjournals.com)

  • Like 4
Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

By using this site you agree to our Terms of Use and Privacy Policy. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.