New Battlefield/Hwy65 interchange
Project
Replace Battlefield Road bridge over Route 65
Convert interchange to a Diverging Diamond Interchange design, which allows
Battlefield Road traffic to make “free” left-hand turns onto Route 65
Build a southbound and a northbound auxiliary lane on Route 65 to connect
the Sunshine Street and Battlefield Road ramps.
Install new traffic signal at Battlefield Road and Woodstock Avenue
Construction Schedule:
November 2014-January 2015
Build auxiliary lanes along Route 65 between Sunshine Street and Battlefield Road
January 2015-May 2015
Replace south half of Battlefield Road bridge over Route 65
Convert interchange to Diverging Diamond traffic pattern
Raise ramps on south side of interchange to meet higher bridge
Improve intersection of Battlefield Road and Woodstock Avenue and install new traffic signal
May 2015-August 2015
Replace north half of Battlefield Road bridge over Route 65
Raise ramps on north side of interchange to meet higher bridge
August 2015-September 2015
Open Diverging Diamond interchange to two lanes in each direction
Build new islands and medians
Completion: September 30, 2015
Project cost: $12.5 million